Annual distribution of budget amounts

Support Center

IC11720

Navigation to this function

The calculated budget values per year are stored in this table.


Identification

Information on the data record’s identification is entered in this section.
PropertyDescription
Project budgetDisplays/select the project budget from which the amount is reserved.
YearEnter the year for which the reservation is made.

Budget values

The budget values are managed in this section. Only the amount to be reserved can be entered. The remaining values are calculated from the project budget project task budget management.
PropertyDescription
Reserved amount [€]Enter the amount to be reserved in Euros.
Planned budget [€]Displays the budget that has already been planned and which therefore is no longer available. It is calculated automatically from the budget planned for the budget positions.
Estimated costs [€]Displays the estimated costs for the project. The costs are calculated automatically from the sum of the assigned contracts and orders for the entire duration of the project.
Actual costs to date [€]Displays the actual costs to date for the project. This is calculated automatically from the costs and invoices assigned to the budget positions.

Recalculate budget values

Recalculation and updating of budget values