This article explains how to set up eTASK.Maintenance. It uses an example to describe the process from a blank system to the first automatically triggered order.

Example: You want to organize your elevator maintenance using eTASK.Maintenance. You have your elevators inspected every two months. Your own company handles the coordination on the contractor side. The elevator inspections are performed by a service provider.

Prerequisite

  • The maintenance workflow is installed.

  • The elevator records are available (objects)

  • The records for your own company and the service provider are available (company table)

  • The personnel records for the asset manager, the coordinators on the client and contractor sides, and the person performing the work are available (Personnel List)

  • Now create a work order (Technical Building Management - Maintenance - Create New Work Orders - Recurring Work Order) and enter the following data:

Procedure in the FM Portal

  1. Create an order plan (Technical Building Management - Maintenance - Create New Orders - Recurring Order) and enter the following data.

  2. Screenshot of eTASK form for configuring recurring maintenance tasks, showing fields for identification, scope, operator, client, and contractor details
    Screenshot of eTASK form for configuring recurring maintenance tasks, showing fields for identification, scope, operator, client, and contractor details

Tip: You can also create a new order plan via the measure record.

Features

Data

Measure

Measure created in step

Object/Asset Manager

Person responsible for the objects in the order plan

Company

Client company

Coordination group

Responsibility created in Step 5: Client Coordination

Client coordinator (optional)

Client-side coordinator

Contractor (AN)

Service provider company

Responsibility: Contractor (AN) Coordinator

Responsibility for coordinating the contractor created in Step 5

Contractor coordinator (optional)

Contractor-side coordinator

  1. After saving, select the elevators in the Object Selector info area.

  2. In the Order Trigger Dates info area, fill in the date selection for the first "Execution by" date.

    Screenshot of eTASK settings dialog:
    Screenshot of eTASK settings dialog: "Termine der Auftragsauslösung" with date field, checkboxes for planning options, and end date field

  3. Click Save in the toolbar.

  4. In the Workflow section, click Activate.

The orders have been created (Technical Building Management - Maintenance - Order List). The workflow is active.

Note: The number of orders automatically triggered at once is subject to certain restrictions. 📄 Einschränkungen bei der automatischen Generierung von wiederholten Aufträgen IC1217